We recently prepared a floor of around 5000m2 in Coalville using a combination of Captive Shot Blasting and Diamond Grinding.
The first phase of the job involved Captive Shot Blasting around 1000m2 of a very hard power floated concrete slab.
The second phase of the work involved Captive Shot Blasting around 450m2 of extremely rough concrete in readiness for repairs.
A further area of around 2000m2 prepared by Diamond Grinding during the second phase.
The third phase of the work involved Diamond Grinding an area of around 1600m2 to remove existing coatings.
We achieved a very high standard of finish throughout all ready for resin application.
Using our ever dependable and solidly built equipment supplied by Blastrac (now Husqvarna) and PPC we are ready to tackle any flooring project across the United Kingdom.